Budgeted Cost Baseline 

Earned-value analysis. A project budget calls for the following expenditures:

 

Task

 

Date

 

Budgeted Amount

 

Build forms

 

April 1

 

$10,000

 

Pour foundation

 

April 1

 

$50,000

 

May 1

 

$100,000

 

Frame walls

 

May 1

 

$30,000

 

June 1

 

$30,000

 

Remaining tasks

 

July 1 and beyond

 

$500,000

 

Define each term in your own words, calculate these values for the above project, and show your work:

 

Budgeted cost baseline (make a graph illustrating this one)

Budget at completion (BAC)

Planned value (PV) as of May 1

Earned value (EV) as of May 1 if the foundation work is only two-thirds complete. Everything else is on schedule.

SV as of May 1.

Actual cost as of May 1 is $160,000. Calculate the cost variance (CV) as of May 1.

Schedule performance index (SPI)

Cost performance index (CPI)

Estimate to complete (ETC), assuming that the previous cost variances will not affect future costs

Estimate at completion (EAC)

0 replies

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply